Electricity Constraint From Gas Reduces to 2,824MW

AD


Gas supply to electricity generation companies (GenCos) which resulted in a shortage of 2,941 mega watts (MW) on Monday reduced to 2,824MW on Wednesday, according to the Nigeria Electricity Supply Industry (NESI) on Friday.
As a result of militants’ attacks on the gas pipelines in the Niger Delta region, lack of gas caused a shortage of about 4,000MW in the last few months and 3,000 MW a fortnight ago.
NESI in its report on electricity performance, noted that on the day under review, the power sector recorded 472.6MW line management constraint, 40MW high frequency constraint and 0MW water management constraint, which all resulted in estimated loss of an equivalent of N1.6b.
According to NESI, “On September 21 2016, average power sent out was 3447MWh/hour (down by 286MWh/h) the reported gas constraint was 2824MW. The reported line constraint was 472.6MW and the reported high frequency constraint is 40MW according to TCN. The water management constraint was 0MW.The power sector lost an estimated N1, 602, 000, 000 on September 21 2016 due to constraints.”
The Nigeria Electricity System Operator (SO), in its Operational Performance report of September 23 noted that at 06:00 of the day under review was 3,992.30MW.
It added that peak generation for the previous day was 4,178MW, lowest generation 3,348MW and energy sent out to the distribution companies (Discos) was 3,596.6MW.