Electricity output dropped by 1,000MW last week due to shut down of four power plants, days after celebrating rise in electricity generation.
According to the website of the Nigerian Electricity System Operator (SO), which is operated by the Transmission Company of Nigeria (TCN), reports that the latest collapse brought the total number of affected power plants to ten.
It noted that, “Electricity from the nation’s biggest power station, Egbin, located in Lagos, hit a record low of 246MW on Saturday from 425MW on Friday, while output from the Shiroro Power Station in Niger State, one of the nation’s hydropower plants, hit a high of 600MW.
It added, “The plants that were shut down after the collapse included Olorunsogo I and Olorunsogo II in Ogun State; Omotosho II in Ondo State; and Ihovbor located in Edo State, with installed capacities of 294MW, 500MW, 500MW and 225MW respectively.”
According to website, on Friday the Olorunsogo II and Omotosho II plants generated 171MW and 83.5MW, while Olorunsogo I and Ihovbor produced 148.1MW and 165.6MW, respectively.
It added that the units GT1 and 3 of Olorunsogo II were said to be untied after the system collapse on September 16; while GT2 and ST2 were out due to gas constraints; GT4 out due to water leakage on the generator cooler; and ST1 out on maintenance.

Meanwhile, most of the generating capacity in Nigeria comes from gas-fired plants and hydro, the country is seeking alternative source to generate power that is sustainable and affordable.

The Nigerian Electricity Regulatory Commission (NERC) disclosed in August that it has made some amendments to accommodate and promote investments in renewable energy sector in Nigeria.
Among the amendments recommended by NERC include an attractive renewable energy feed-in-tariff and a regulation that ensures that local electricity distribution companies (Discos) source up to 50% of their power from renewable sources.
The electricity regulatory commission noted in a renewables seminar last month that another adjustment will be a long-term cost recovery cycle as additional significant incentive to make Nigeria become a choice destination for renewable energy investors.