Press Release: RE:Disconnection of University of Calabar Teaching Hospital, The True Story-PHED

AD


The attention of the Port Harcourt Electricity Distribution Company, PHED has been drawn on the print media publication bothering on the above subject matter.
Ordinarily, we would not have responded to the issue as it is not in our policy to engage our esteemed customers including University of Calabar Teaching Hospital, UCTH, in what may be termed media war but for the purpose of stating the true position of the story as it tends to portray PHED in bad light.
Port Harcourt Electricity Distribution Company, PHED, came into existence on 1st November 2013 as one of the eleven Distribution Companies in the country after successful privatization by the federal Government of Nigeria.
It’s responsibilities include among others to distribute electricity [power] in four states namely;Akwa Ibom, Bayelsa, Cross River and Rivers at a cost  to various categories of  customers and  collect  same in order to offset the cost of supplying gas to the generating stations  and the cost of wheeling the power through the Transmission Company of Nigeria, TCN, to PHED.
Stemming from the above, Port Harcourt Electricity Distribution Company, PHED, does not just disconnect customers for non-payment of bills, it has a process of doing that in line with the directive of Nigerian Electricity Regulatory Commission, NERC.
As a responsive company, the due date of disconnecting customers is imprinted on the bills of customers notifying them of the due date of disconnection which is 15th of every month.
Apart from the above, premium customers such as UCTH are always notified in writing about the company’s intention to carry out disconnection if all attempts through relationship marketing fail.
It is pertinent to state that each Maximum Demand customer has a specially trained key accounts officer attached to it in order to resolve any billing or technical issue[s] that may arise.
In the case of UCTH, several visitations were made to their office from May to July 2016 with a view to making them see reasons why the outstanding bills should be paid but the response was not forthcoming, hence the first disconnection on 28th July 2016.
The disconnection on the said date prompted UCTH to have a meeting with PHED and thereafter, it was reconnected on 2nd August 2016  based on the letter of commitment by the Deputy Chief Medical Director, Dr Joe Udosen, who committed the Teaching hospital to offset the debt  using an agreed payment plan.
This eventually, paved way for a meeting also in the office of the Chief Medical Director, Professor Thomas Agan on  16th  August, 2016  where PHED formally delivered a letter, titled “Need to settle outstanding PHED energy bill”, amounting to  N35,367,938.70 and the need to pay or face disconnection,[Ref;PHED/PaCM/vol3/215/2016]
The above outstanding debt was not a month’s bill as claimed but an accumulated bill arising from irregular paltry payments .
PHED admits that the teaching hospital had a faulty meter and was billed on estimate based on the approved NERC methodology through load assessment and the perceived over billing by them is as a result of the amount of energy being wheeled to the hospital taking into cognizance its importance in health service delivery. The hospital is on Amika 33kv line which is a priority feeder.
For instance, the hospital consumes an average of 98,766kwh in month on a tariff of N46.73 on A3.
On 4th August 2016 when a functional meter was installed, the bill accrued between that date and 29th August 2016 has risen to N2,955,128.13  based on  meter reading.
Therefore, PHED wishes to state categorically that against all odds as being peddled in the media, established consultations with the management of the Teaching Hospital were made and due process was followed by PHED before disconnection was carried out in the second week of September 2016. It was a last resort in recovering the huge debt.
Setting the law aside, it may interest you to know that the hospital has reconnected itself illegally four days ago without paying a dime; however, our team has once again disconnected it.
Finally, PHED recognizes UCTH as one of its customers established to make life better for Nigerians through good health care services but members of the public should also realize that PHED is out to improve its service delivery when customers pay for what they have consumed.
 John Onyi
Communications Lead,
Port Harcourt Electricity Distribution Company.