Outage Alert: Lagos

AD

Spark Outage Alert

Ikeja Electricity Distribution Company has announced that there will be planned outage at the Ikorodu Transmission Station. The reason for the outage is to enable the installation of an additional 60MVA,132/33KV Transformer. The planned outage will affect three 33kv feeders namely; Spintex, Ijede and T2 15MVA, 33/11kv. While four 11kv feeders will be affected at Sabo Injection Substation i.e Lasunwon, Ladega, Eyita and Igbogbo feeders. This outage will commence on 2nd February 2017 and end on 16th February 2017. Customers on the affected feeders will be back-fed from alternative feeders during the period and this will result in load shedding.